Frameworks

Procure Partnerships Frameworks 2027: £14bn Plans Explained

Procure Partnerships is consulting on £14bn of construction and civil engineering frameworks for 2027. Check the proposed lots, dates and contractor actions.

UK public building and bridge construction representing the proposed £14bn Procure Partnerships frameworks for 2027

Procure Partnerships Framework and Wirral Council have opened preliminary market engagement on two proposed agreements with a combined estimated value of £14bn. The plans comprise an £8bn National Construction Framework and a new £6bn Civil Engineering & Infrastructure Framework, both expected to start on 13 October 2027 and run for four years.

Interested contractors can respond to questionnaires on The Chest by 3pm on Friday 15 January 2027. This is market engagement, not an invitation to tender. The proposed values, lot structures and timetable remain indicative and may change before the tender notices are published.

The two proposed Procure Partnerships frameworks compared

National Construction Framework Civil Engineering & Infrastructure Framework
Estimated value £8bn excluding VAT £6bn excluding VAT
Proposed term 13 October 2027 to 12 October 2031 13 October 2027 to 12 October 2031
Main scope Construction, fit-out and M&E Five civil engineering and infrastructure workstreams
Geographic model Sub-regional, regional and North, Midlands and South lots Sub-regional and North, Midlands and South lots
Proposed lot count 123 220
Suppliers Up to 12 anticipated per lot Up to 12 anticipated per lot
Questionnaire The Chest reference DN836612 The Chest reference DN836900
Engagement session 11am, 26 January 2027 11am, 2 February 2027

The £14bn is a forecast of potential activity, not guaranteed expenditure or revenue for appointed firms. Both official notices say suppliers that do not take part in this engagement will not be excluded from, or disadvantaged in, the later procurement.

Proposed National Construction Framework lots

The National Construction Framework is the planned renewal of Procure Partnerships' national construction arrangement. Its general construction element excludes the North West, which is covered by the separate North West Contractor Framework. Fit-out and M&E lots include all nine English regions, including the North West.

The indicative structure contains:

  • Construction: £50,000 to £500,000, £500,000 to £2m and £2m to £10m across 15 sub-regions.
  • Construction: £10m to £20m across 13 sub-regions, with the North East and Yorkshire and the Humber each treated as one area.
  • Construction: £20m to £40m across eight English regions outside the North West.
  • Construction: £40m and above across North, Midlands and South lots.
  • Fit-out: £50,000 to £2m, £2m to £20m and £20m and above across nine English regions.
  • M&E: the same three bands and nine-region structure as fit-out.

The construction lots total 69, while fit-out and M&E each account for 27, producing 123 proposed lots. The official notice describes Design and Build and Build Only delivery, using direct award, two-stage or single-stage competition and NEC or JCT contracts.

Proposed civil engineering and infrastructure lots

The new Civil Engineering & Infrastructure Framework is planned around five workstreams:

  1. Enabling works and demolition.
  2. Highways and transport.
  3. Water, flood defence and coastal infrastructure.
  4. Utilities, energy and electrical infrastructure.
  5. Regeneration, brownfield and urban infrastructure.

Enabling works and demolition has two proposed bands, £50,000 to £2m and £2m and above, each divided into 14 sub-regions. The other four workstreams have bands of £50,000 to £2m, £2m to £10m and £10m to £30m across the same 14 sub-regions. Projects from £30m to £50m and above £50m use North, Midlands and South lots.

In this framework, the North West is excluded across all workstreams because it sits on the separate North West arrangement. London is divided between two sub-regions: North London is grouped with Thames Valley and Hampshire, while South London is grouped with Kent, Surrey and Sussex.

The 220-lot total comprises 28 enabling and demolition lots plus 48 for each of the other four workstreams. These arrangements are proposals being tested through engagement, rather than final tender requirements.

Confirmed dates and how to participate

The two UK2 preliminary market engagement notices were published on 24 November 2026. They give the following timetable:

  • 15 January 2027 at 3pm: deadline stated in both notices for returning the relevant questionnaire through The Chest.
  • 26 January 2027 at 11am: online engagement session for the National Construction Framework.
  • 2 February 2027 at 11am: online engagement session for the civil engineering framework.
  • 12 April 2027: estimated publication date for both tender notices.
  • 13 October 2027: estimated start date for both agreements.

Use The Chest references DN836612 and DN836900 to find the questionnaires. Completing the relevant questionnaire registers interest in the online engagement session. It is not a tender submission or an application for a framework place.

Read the official National Construction Framework notice and Civil Engineering & Infrastructure Framework notice before responding. Procure Partnerships has also published an overview of both proposals.

What this means for main contractors and specialists

The lower value bands and sub-regional areas appear designed to give established regional contractors a credible direct route. The notices ask for parties with a proven track record in the relevant works, but final eligibility, financial thresholds and assessment criteria will only be known when the tender documents are published.

For a main contractor considering direct appointment, the immediate decision is which workstream, value band and geography match its evidence and delivery capacity. A place on a framework would still not guarantee call-off work. Buyers could use direct award where the eventual framework terms allow it, or run single-stage and two-stage competitions.

Most specialist subcontractors will not seek a direct framework appointment unless the final scope allows and their business can meet the lot requirements. Their route is more likely to be through the supply chains of appointed main contractors. Those are separate commercial positions: securing a framework place provides a contractor with access to potential call-offs, while building relationships with appointed contractors can lead to subcontract opportunities after projects emerge. Neither route guarantees work.

What construction businesses should do now

Contractors interested in a direct place should review the proposed lots against turnover, project values, geography and reference projects. Responding to market engagement offers a chance to comment on whether the proposed structure is workable. It also provides access to the relevant online session.

Prepare an evidence register covering comparable schemes, contract values, client references, delivery model and regional capacity. Review insurance, financial information, carbon reduction, social value and payment performance evidence, without assuming these will be the final selection criteria. Monitor the official notice for amendments and the expected April tender publication.

Specialists can map the contractors likely to pursue their relevant lots and improve the project evidence those firms will see when supply chains are assembled. Start with the Market Maestro Framework Calendar and our guide to getting on a construction framework. The approved contractor list guide explains the distinct supplier onboarding route used by many main contractors.

Market Maestro helps construction firms present relevant experience clearly to target contractors and public sector buyers. If your team needs a focused plan before the 2027 procurement cycle, speak to Jude about your target market.

Continue reading

Related insights

FRAMEWORKS

How to Prepare for a Construction Framework Application

Find the correct route, assess fit and organise evidence against the actual framework requirements.

Framework Strategy

How to Use the Framework Calendar (And Why Most Contractors Check It Too Late)

Use the UK construction Framework Calendar to check procurement stages, prepare project evidence and research relevant supply-chain opportunities.

Tender Guide

Construction Tenders: Separate the Invitation, Qualification and Award

Understand what each stage requires and use specific project evidence in responses rather than relying on marketing claims.